Friday 27 August 2010

Central Mast Beam - Three Sections Made!

The three sections of the mast beam are now complete. Laid out, they give an indication of how beamy the boat will be ... very!
A bit of sanding and a coat of epoxy to keep things dry will complete the work on these for now. Just need to find somewhere to store them.



Tuesday 17 August 2010

Mast Beam - Central Section

The first section of the Gypsy Sophia to build is the central section of the mast beam. I am having to get used to working with epoxy again, and in particular making sure I don't mix more that I need at a time - it is far too expensive for that. It's amazing how a few bendy bits of wood become a rigid structure once glued together. An investment in a goodly number of clamps has been well worth it - especially at £2.50 each from Screwfix!





Friday 6 August 2010

First cut!

I suppose I can't claim to have started building until I have stuck two bits of wood together. However, having cut into the first sheet of plywood is very satisfying. First cut is the mast beam inner ply webs.


Sunday 1 August 2010

The first materials!

The project has really begun now with the arrival of the first 9 sheets of plywood, and 12 litres of epoxy resin. All that remains now is for a bit of cutting and sticking! Watch this space!